[International] Brazil POSCO Construction CSP Steel Plant Project Water Treatment Plant Wort Construction
Client: - Contractor: Daeah E&C
Scope of work: Defect Repair Works Year of completion: May. 2016
-
[International] Uruguay Punta del Tigre Combined Cycle Power Plant HRSG TUBE defect repair work
Client: - Contractor: Daeah E&C
Scope of work: Defect Repair Works Year of completion: Mar. 2016
-
[Domestic] Yeongheung Thermal Power Coal Handling Facility Planned Preventive Maintenance Work
Client: Korea South-East Power Contractor: Shinheung Construction
Scope of work: Maintenance Works Year of completion: Mar. 2016
-
[Domestic] Taean IGCC outage work defect maintenance work
Client: Korea Western Power Contractor: Doosan Heavy Industries & Construction
Scope of work: Defect Maintenance Works Year of completion: Feb. 2016
-
[Domestic] Yeongheung Thermal Power Plant #5 OVER HAUL coal handling facility construction (KEPCO Industrial Development)
Client: Korea South-East Power Contractor: KEPCO Industrial Development
Scope of work: Overhaul Works Year of completion: Oct. 2015
-
[Domestic] Shinboryeong Thermal Power Plant #1, 2 steel frame modification and installation work
Client: Korea Midland Power Contractor: Doosan Heavy Industries & Construction
Scope of work: Installation Works Year of completion: Jun. 2015
-
[Domestic] Shinboryeong Thermal Power Plant #1, 2 boiler tube welding and installation work
Client: Korea Midland Power Contractor: Doosan Heavy Industries & Construction
Scope of work: Installation Works Year of completion: Apr. 2015
-
[International] Bongjung Thermal Power Plant 2 Boiler Furnace Scaffolding Installation Work in Vietnam
Client: - Contractor: Doosan Heavy Industries & Construction
Scope of work: Installation Works Year of completion: Feb. 2015